1/5
The Project won the Global Best Project Award of Merit for Airports announced by ENR.
The $1.1 billion North Terminal Development Program is a portion of the larger $2.95 billion Miami Airport North Terminal Development, created to handle the ever-increasing passenger traffic demands at Miami International Airport. Odebrecht in Joint-Venture (50/50 joint venture) is the general contractor for the central element of this development, contracted with Miami-Dade County under an at-risk contract of more than $1.1 billion. The work by Odebrecht entails 1.8 million square feet of new terminal and concourse construction, integrated into an additional 1.5 million square feet of terminal renovation and remodeling at the existing operational facility.
The North Terminal, more than 1 mile in length, is one of the largest and more complex expansions of an existing airport in the United States, with the magnitude of the development roughly equating to building a new mid-sized airport within a fully operating facility. Highlights of the development include 50 new passenger gates; a new Federal Inspection Services (FIS) facility; 123 ticket counter positions; 119 self-service ticketing kiosks; 72 FIS passenger booth-processing-positions capable of processing 3,600 international visitors per hour; a state-of-the-art baggage handling system capable of handling 45,000 bags per day; nearly 2 miles of escalators and moving walkways; a four-station elevated automated people mover system (the Skytrain) running along the roof of the new terminal; a wide array of concessions, offices, facility support, and customer services areas.
Initial and Final Construction Cost, including Change Orders
Initial Contract Amount: $1,045,501,216
Final Contract Amount including Change Orders: $1,113,501,216
Type of Contract and the Stage of Design or Construction that the construction contract was agreed upon: Initially, this contract started as Construction Management at Risk contract with fixed fees for staff, home office overhead and profit and the Owner budgeted direct cost
allowance and general conditions. Preconstruction services were also provided under this contract structure. Odebrecht also inherited some unfinished projects that were completed under a GMP structure called “Annex”. The direct cost on these GMPs was established through a publicly bid process jointly with the Owner.
Before construction started in March 2007, the contract was converted to a lump sum hybrid general contractor and construction management services, where the Owner identified Odebrecht as the Managing General Contractor. This resulted in the largest general contractor contract issued by any government entity in the state of Florida.
In June 2005, the original contract included ten different design projects, in which only three projects were ready for construction and the remaining seven the construction documents were between 50% to 75% complete. During preconstruction services, the owner requested that constructability reviews were performed in all ten design projects but only eight projects were actually built. Throughout the entire course of the North Terminal Development Program, there were over twenty design projects ranging from $200 thousand to over $90 million added by the owner.
Dates services were performed for the project:
Preconstruction Services – August 2005 to March 2007
Completion Projects – August 2005 to March 2007
Construction – March 2007 – July 2012 (forecasted completion date)
LOCATION: Miami, Florida
CLIENT: Miami-Dade Aviation Department
CONTRACTED BY: Parsons-Odebrecht, JV
INDIVIDUAL ROLE: Alexander Mowzoon,
Sr. Project Manager/
Corporate QA/QC Manager